About
The Village of Ruidoso has begun a project to provide comprehensive analysis, design, and replacement for six bridges located within residential neighborhoods in the Village. This project stems from the original damage that occurred in 2008, while responding to the urgent infrastructure needs of today, wrought by the significant additional damages resulting from recent wildfire and subsequent flooding events. Several of these bridges serve as the sole access routes to their respective communities, making their restoration critical to public safety, emergency response, and the long-term resilience of local transportation networks. The project locations are:
-
McDaniel Dr
-
North Loop
-
Main Rd 2
-
Sleepy Hollow Rd
-
River Trail
-
Robin Rd
This project will include site investigations, hydrologic and hydraulic analyses, environmental compliance, structural design, permitting, and construction of six bridges. The design will prioritize improved resilience to future wildfire and flood events, compliance with current engineering standards, and minimization of community disruption during construction.
This critical infrastructure improvement project will enhance safety, restore essential connectivity, and support the long-term recovery and hazard mitigation goals of the Village of Ruidoso.
Community Engagement Opportunities
Return to the project website to find out about public meetings, questionnaires, and to leave a comment on the interactive map!
Public Meetings
Join one or both of the first set of public meetings to learn about the Ruidoso bridge replacements and share your questions and concerns. All are welcome at either and/or both meetings.
Tuesday, June 16, 2026
5:30-7pm
![Flyer #1 [05-21-26]_Page_1.png](https://static.wixstatic.com/media/18db8f_20a1fb27c3254424a84c4982642569f6~mv2.png/v1/crop/x_0,y_0,w_3300,h_2541/fill/w_980,h_755,al_c,q_90,usm_0.66_1.00_0.01,enc_avif,quality_auto/Flyer%20%231%20%5B05-21-26%5D_Page_1.png)
Ruidoso Convention Center, 111 Sierra Blanca Dr
This meeting will provide an overview of the project and allow for members of the community to interact with the project team and village staff, and will focus the McDaniel Dr, North Loop, and Main Rd 2 locations.
Wednesday, June 17, 2026
5:30-7pm
![Flyer #1 [05-21-26]_Page_1.png](https://static.wixstatic.com/media/18db8f_20a1fb27c3254424a84c4982642569f6~mv2.png/v1/fill/w_980,h_757,al_c,q_90,usm_0.66_1.00_0.01,enc_avif,quality_auto/Flyer%20%231%20%5B05-21-26%5D_Page_1.png)
Ruidoso Convention Center, 111 Sierra Blanca Dr
This meeting will provide an overview of the project and allow for members of the community to interact with the project team and village staff, and will focus on the Sleepy Hollow Rd, River Trail, and Robin Rd locations.
Public Meeting Flyer
Click the button below to download a flyer which details the upcoming public meetings for this project.
Share Your Thoughts
Is there anything that you would like share with the project team as we begin design of the new bridges?


Anticipated Timeline
Design and construction of the bridges will be phased.
Spring
2026
Project Kick Off
Summer - Fall
2026
Public Meeting, Drainage Analysis, 30% Design
Fall - Winter
2026
Begin Environmental Assessment, Public Meeting, 60% Design
Winter 2026 - Spring 2027
Public Meeting, 90% Design
2026
2027
Spring - Summer
2027
100% Design
Summer - Fall
2027
Bid Opening
Fall 2027 - Summer 2028
Construction
Contact Us
If you have quesitons or concerns, please get in touch with the project team using the phone number or email below!